Encouraging manager and analytical problem-solver with talents for team building, leading and motivating, as well as excellent customer relations aptitude and relationship-building skills. Proficient in using independent decision-making skills and sound judgment to positively impact company success. Dedicated to applying training, monitoring and morale-building abilities to enhance employee engagement and boost performance.
Work Details:
Client: El Amrya Petroleum Refining Company (APRC)
Project: Supply and Installation of 108 Radar Tank gauging for Tanks
Position: Project manager
Activity:
APRC company request a complete Radar tank gauging for 108 tanks included Temperature transmitter and Pressure gauge as complete system, with Control and monitoring system.
I was responsible
Client: Egyptian linear alkyl Benzene Company (ELAB)
Project: Design and construction of new storage 4 tanks
Position: Project manager
Activity:
ELAB company request a new storage tank area included Mechanical, Civil, Electric, Instruments works with tie-in the existing area,
I was responsible
Client: Gulf of Suez Petroleum Company (GUPCO)
Project: Replacing and Integration of Instrument Devices (Offshore)
Position: Project manager
Activity:
Review of engineering drawing, shop drawings, supervision of installation of
Client: Misr Petroleum Company
Project: Flow Metering Skids Using for Trucks Loading - EMERSON
Position: Project manager
Activity:
Client: El Nile Petroleum Company
Project: Flow Metering Skids Using for Trucks Loading - EMERSON
Position: Project manager
Activity:
Client: The Petroleum Projects & Technical Consultations Company (PETROJET) - IRAQ
Project: Laying of Power, Instrument and Fiber optics cables at Siba Field - IRAQ
Position: Project manager
Activity:
Client: Italfluid Company
Project: Establish of the new Compression station at Meliha Field
Position: Project manager
Activity:
Work Details:
Client: Agiba Petroleum Company
Project: Ashrafi Offshore platforms rehabilitation (Brown filed-Offshore)
Position: E&I site manager
Activity:
The project involves rehabilitation to 3 platforms in Gulf of Suez, the projects includes three instrument and control sub projects:
Client: Egyptian Natural Gas Company (GASCO)
Project: Installation of Low voltage switch gear
Position: E&I site manager
Activity:
Client: Qarun Petroleum Company
Project: Gas Compression Plant
Position: E&I site manager
Activity:
Client: El-wastani Petroleum Company (WASCO)
Project: Gas Development Project.
Position: E&I site manager
Activity:
Client: Co-Operation Petroleum Company (CO-OP)
Project: Construction of Shipping umbrella for Petroleum Products and construction of new pumps station
Position: E&I site manager
Activity:
Client: Arab Petroleum Pipelines Company (SUMED)
Project: Installation of fire detection and alarm with extinguishing system.
Position: E&I site manager
Activity:
Client: AGIBA Petroleum Company
Project: Installation new 5th turbine at Melieha field
Position: E&I site manager
Activity:
Work Details:
Client: Wepco petroleum Company
Project: Upgrading El- Hamra Terminal
Position: Electrical Engineer
Activity:
Review of engineering drawing & construction supervision of install a new Cathodic protection for the new tank.
Client: Khalda Petroleum Company
Project:
New Storage tank 5000 m3
Position: Instrument Engineer
Activity:
Client: Alexandria National Refining Petroleum Company (ANRPC)
Project:
Installation of the new Switch gear and transformers
Position: Electrical Engineer
Activity: