Review all shop drawing for infra-structure works (drainage networks, fire networks and irrigation
Networks)
Coordinate infra-structure services via road another trades
Follow up the S/C for all shop drawings, progress…
Etc
Review the drawing with consultant to get approval for submitted shop drawings
Solve site problems and make modification on drawings according to site situation
Review the design drawings and figure out the issues and rise the relevant RFI’S
Check BOQ, Vendor list and compare with design drawings
Review shop drawing for all firefighting and sprinklers distribution works
Review shop drawing for drainage network underground and high level
Review shop drawing for drainage toilet details
Review shop drawing for water Supply toilet details.
Technical office Team Leader
Badr El-Din Group
1st Floor, Bldg.1, Arkan Mall, El Sheikh Zayed, Giza, Egypt
06.2019 - Current
Designing, revising, following up, coordination with client and contractor sides, preparation of project specifications and the other tender document and for Air conditioning and ventilation systems, Fire Fighting system, Plumbing system and Infra structure.
Design review Preparing Cost Estimate.
Contractor’s Technical office for Engineering services, preparing shop drawings, Re-calculation,reviewing, design drawings, tender documents, material submittals in accordance with project specifications.
Complete site supervision of mechanical works includes Shop drawings review, and material submittals and site supervision on contractor works.
Mech. Tech. Office Engineer
Scope, MALL OF EGYPT
01.2017 - 01.2019
Review shop drawing for all firefighting and
sprinklers distribution works
Review shop drawing for drainage network
underground and high level
Review shop drawing for drainage toilet details
Review shop drawing for water Supply toilet details
Prepare shop drawing for firefighting and domesticwater
supply Pump room
Review shop drawing for submersible pumps details
Review shop drawing for riser diagram for watersupply
and drainage system
Coordination for the MEP trades with structureworks
and architecture
Make coordination with firefighting and HVAC workswith
false celling drawings
Review all shop drawing for infra-structure works
(drainage networks, fire networks and irrigation
Networks)
Coordinate infra-structure services via road andother
trades
Review the design drawings and figure out the issues and rise
the relevant RFI’S
Check BOQ, Vendor list and compare with design
drawings
Quantity survey for all mechanical items according to
approved material submittals and approved shopdrawings
1Follow up the S/C for all shop drawings, progress…
Etc
Review the drawing with consultant to get approvalfor
submitted shop drawings
Solve site problems and make modification on
drawings according to site situation
ASSIGNED
Mech. Tech. Office Engineer
CAIRO FESTIVAL CITY MALL
01.2013 - 01.2017
Prepare shop drawing for all firefighting and
sprinklers distribution works
Prepare shop drawing for drainage toilet details
Prepare shop drawing for water Supply toilet details
Prepare shop drawing for firefighting and domesticwater
supply pump room
Prepare shop drawing for submersible pumpsdetails
Coordination drawings for the MEP trades with
structure works and architecture
Make coordination with firefighting, HVAC workswith
false celling drawings
Make coordination with all infra-structure works
Review the design drawings and figure out the issues
and rise the relevant RFI’S
Check BOQ, Vendor list and compare with design
drawings
Prepare and review shop drawing for all infra- structure
(drainage networks, fire, networks, and irrigation
Solve site problems and make modification on drawings
according to site situation.
Scope
01.2012 - 01.2013
1- Prepare shop drawing for all firefighting and
sprinklers distribution works
2- Prepare shop drawing for water Supply toilet details.3- Make
coordination with all infra-structure works
4- Review the design drawings and figure out the issuesand rise
the relevant RFI’S
5- Prepare and review shop drawing for all infra- structure
(drainage networks, fire, networks, andirrigation.
Designer Engineer
EL-BEEHA ENGINEERS
Naser City
01.2011 - 01.2012
Prepare design drawing for firefighting system
Prepare design drawing for infra structure works and plumbing works
Prepare design drawing for water and drainage toilet details
Manual calculation for HVAC system and hap
External Static pressure calculation for FCU
Education
BSc - Civil Engineering
Banha Engineering University
Banha
06.2006 - 06.2011
1- HVAC.
2- Infra Structure
3- Firefighting. - undefined
Skills
Date of birth: 21/6/ 1989undefined
Additional Information
asuitable position at your esteemed company
Certification
Project Management Professional (PMP)®
Timeline
Project Management Professional (PMP)®
01-2023
Technical office Team Leader
Badr El-Din Group
06.2019 - Current
Sr. Mech. Tech. Office Engineer
MINISTRY OF DEFENSE
06.2017 - 01.2019
Mech. Tech. Office Engineer
Scope, MALL OF EGYPT
01.2017 - 01.2019
Mech. Tech. Office Engineer
CAIRO FESTIVAL CITY MALL
01.2013 - 01.2017
Scope
01.2012 - 01.2013
Designer Engineer
EL-BEEHA ENGINEERS
01.2011 - 01.2012
BSc - Civil Engineering
Banha Engineering University
06.2006 - 06.2011
1- HVAC.
2- Infra Structure
3- Firefighting. - undefined